Engineered oak timber floor in a waterfront restaurant dining room at Constitution Dock.
Portfolio Case Study

Constitution Dock Restaurant: Engineered Oak in a Working Kitchen's Shadow

An engineered oak dining floor detailed to survive service traffic, spilled wine and a waterfront humidity swing.

Project Category
Commercial Hospitality
Location
Hobart Waterfront, TAS
Material Selection
Engineered European Oak
Installation Time
10 Days

The Challenge & Vision

A waterfront room that swings from damp winter mornings to a full house on a summer evening, with the humidity range that implies. Solid timber would have cupped within a season. The owners still wanted a real oak surface underfoot in the dining room, and the fitout window was the ten days between Christmas and the January trade.

Engineered oak boards being laid through an empty waterfront dining room.
Engineered oak fully bonded to the slab, showing the 4mm wear layer at a cut edge.

The Solution

A 14mm engineered board with a 4mm oak wear layer over a birch ply core — dimensionally stable across the humidity range in a way solid stock is not. Fully bonded to the slab rather than floated, so there is no hollow sound under service traffic, and finished in a commercial-grade matt polyurethane that takes red wine without staining.

Total Area
240m²
Total Area
Wear Layer
4mm Oak
Wear Layer

Project Details

Client
Constitution Dock Restaurant
Location
Hobart Waterfront, TAS
Total Area
240 sqm
Timeline
10 Days
Material
14mm Engineered Oak, 4mm Wear Layer

Watch the Installation

Ten days of engineered oak going down through the dining room, condensed into a short walkthrough.

Project Roadmap

Ten days between the Christmas close and the January reopening.

  1. Day 1: Survey

    Slab moisture tested and the room mapped for level across 240sqm.

  2. Day 2–3: Prep

    Old floor lifted, slab ground back, moisture barrier and primer applied.

  3. Day 4–8: Fit

    Engineered oak fully bonded, board by board, from the window wall inward.

  4. Day 9–10: Finish

    Commercial matt polyurethane applied and cured ahead of reopening.